Our Projects

Dig into a few of our favorite portfolio projects:

Thanksgiving Elementary

Tractor Supply Company

TOC Access Road

Regional Commerce Center

Thanksgiving Elementary

cubic yards of dirt moved

miles of utilities onsite

equipment hours

150,000

Cubic yards of dirt moved

2

Miles of utilities onsite

15,000

equipment hours

The Job

The Thanksgiving Elementary project involved a First Third Party School Grading & Utility Contract. Our services included Site Grading, Utilities, Curb, Stone, and Asphalt. We were able to improve an aggressive construction schedule and deliver the building pads to Wimco prior to milestone dates, which allowed them to begin construction sooner than anticipated. We also intentionally adapted to the project needs by working out of sequence in relation to the cut to fill areas on the project to deliver the building pad.

After completing this job efficiently and fast-paced (45 days ahead of an aggressive schedule!) We won the bid for the onsite Sewer Force Main project that serves the school.

Problems We Solved

We worked together with Wimco to complete our scope of work while still allowing other trades to complete their work. We adapted to complete areas out of sequence as WIMCO turned them over to us in order to not only complete the project on time, but beat our deadline by 45 days. We also did out of sequence grading (Cut to Fill) to get building pad on grade and achieve better construction milestone dates, despite being up against wet winter weather.

Our Partners

WIMCO, Asphalt Services on Demand, Erosion Control Solutions, Green Resource LLC, Hanson Neverson, Mack Industries, Rinker Materials, TEC Utilities Supply, Inc.

Tractor Supply

equipment hours

WMBE participation

partners we collaborated with

4,600

Equipment hours

15%

wmbe participation

9

Partners we collaborated with

The Job

We were hired by WIMCO to do turnkey site development for the new Tractor Supply Company in Clayton, NC. The scope of work included site grading activities, utilities, curb & gutter, stone, and asphalt. Work area included the TSC property and offsite on HWY 42.

We worked hand in hand with WIMCO on workflow and sequence to accommodate the construction of Tractor Supply. We were able to implement a plan for the road widening portion that was delayed due to weather. The plan was executed and the project was able to have the grand opening as scheduled.

Problems We Solved

Winter weather and rain played a big factor in finishing this project. Through coordination with WIMCO and determination of our team, the project was completed and delivered for the grand opening.

Our Partners

We were contracted by WIMCO for the site and utility portion of the project. Our subcontractors included ASD, Capital City C&G, Cable Pavement Markings, Razorback Boring, TEC Utilities Supply, Rinker Materials, Mack Industries.

TOC Access Road and WRF Early Grading

CY of dirt

cy moved off site

lf of waterline

200,000

Cubic yards of dirt

100000

cy moved off site

3500

lf of waterline

The Job

Providence was called in to complete a turnkey site development for the Town of Clayton access road and WRF early grading. This project consisted of erosion control, earthwork, water and storm utilities, and ABC access road to the project.

Success for us was bringing our Will to Win on a demanding project schedule with large scale requirements. We moved over 200,000 CY of dirt, over 100,000 CY of that was moved offsite. We also installed storm drainage and over 3,500 LF of waterline.

Problems We Solved

The schedule and volume were our toughest challenges, but they were no match for our team’s drive to win for our client. 

Ultimately, we delivered the project on time, moving over 200,000 CY of dirt, half of which had to be moved offsite. 

 

Regional Commerce Center

lf of waterline laid

concrete structures set

lf storm drainage pipe removed

7,840

LF of waterline laid

77

Concrete structures set

16,800

LF of storm drainage pipe removed

The Job

wp_ was called in to hit critical milestone dates for the Prime Contractor and General Contractor. The site, in Durham, NC has 410,000 square foot warehouse space with infrastructure to accommodate their utility needs and parking needs. Our scope was 10,000 LF of storm drain, 3,000 LF of sewer, and 8,000 LF of waterline in a 12 month schedule.

Success for us was being flexible to what our client needed as the project progressed. Time was of the essence on this project, and we delivered. Multiple Pond structures were in and completed within 20 days to allow the contractor to continue dirt moving operations. Substantial completion within 12 months.

Whether 1, 2 or 3 crews were needed. wp_ stepped up to whatever resources our clients asked of us. We showed our mutual flexibility by ebbing crews in and out as the dirt moving operations progressed through the project.

Problems We Solved

The schedule was the toughest challenge to ensure we did not hold up the other contractors. We also ran into unforeseen rock but did not waver from hitting our milestone dates. We laid sections of this pipe at depths greater than 20 feet.

Ultimately, we delivered the project on time and attacked the small final punch list expeditiously. Our client was able to turn the project over on time and with the quality product wp_ delivers

 

Have a Project in Mind?

Drop Us a Line

Ed Aldridge

Director of Business Development

919.961.0129